Due to the extreme temperatures, our third concrete pour has been delayed for a few days. It is now scheduled to take place this Monday, July 29th. This third pour will contribute 145 cubic meters of concrete to the 500 cubic meter outlet structure.

Work will be starting at about 3am on July 29th. There will be increased truck traffic on Highway 93 and on Fairmont Resort Road from about 03:00am and 12:00pm. There should be no interruption to traffic, but traffic control will be in place to ensure the safety of the public and workers.

Thank you for your ongoing cooperation during construction.

As always, if there are any questions about the project, please don’t hesitate to contact the project manager at the RDEK, Kara Zandbergen at kzandbergen@rdek.bc.ca.