Grand Opening - Cold Spring Creek Debris Flow Mitigation Project

You are invited to the grand opening of the Cold Spring Creek Mitigation Project as we celebrate with speeches, a ribbon cutting, and refreshments.

When:

  • October 8th at 11 AM
  • Shuttle trips will begin at 10 AM, and the event will begin at 11 AM.
  • You must register in advance for a timeslot on the shuttle by 12 PM on October 7th.
  • Please book the times closest to the event start first (10:45, then 10:30 once the 10:45 slots are full).

Register for the shuttle by clicking HERE.

Anyone with accessibility needs or specific transportation requirements is asked to contact lmcmahon@rdek.bc.ca.

Where:

Attendees will meet at the Mineral Mountain Ziplines parking lot (located to the left of the entrance to the Fairmont Hot Springs parking lot) to take a shuttle to the structure site. No public vehicles will be permitted at the site.

We hope you can join us.

Cold Spring Creek Debris Flow Mitigation Project

The Fairmont Flood & Landslide Service is in place within the community of Fairmont. Within the Service Area, the RDEK has debris flow mitigation infrastructure on both Fairmont Creek and Cold Spring Creek. This infrastructure is regularly inspected and maintained as needed.

After completing a multi-phase debris flow mitigation project on Fairmont Creek in 2018, debris flow mitigation on Cold Spring Creek was identified as a priority project by the RDEK Board in its 2019/2020 Strategic Plan. The project has received significant funding: 98.5% from federal and provincial funding streams.

Construction is complete and MacKay has fully demobilized from the site. Projection completion reporting is ongoing and will be completed this fall.

Other Related Projects in Fairmont

PROJECT UPDATES/NEWS

PROJECT OVERVIEW

We are building a large debris flow barrier that is designed to contain 84,000 cubic meters of debris flow material which is roughly a 300-1000 year return period event. This project will significantly reduce the debris flow risk in the community.

There are a few key construction components:

  1. The Barrier and Outlet Structure: The barrier will be approximately 8m tall above the existing Cold Spring Creek channel with a 3m wide vertical outlet opening at the channel. The outlet will have steel bars that will capture debris but allow water to pass through. The barrier will be constructed of roller compacted concrete (RCC) which is a concrete mixture that is placed in lifts and compacted.
  2. The Creek Diversion and Basin: There will be a basin excavated behind the barrier for debris storage and the creek will be diverted into the basin and will then flow out of the outlet structure which will be located at the existing Cold Spring Creek channel.
  3. The Water Lines: The water lines that service the community are located in the project area. The lines will be reinforced and relocated as part of the project. There will be a brief interruption to the water service to the community later this fall when the new lines are tied in.
  4. The Access Road: An access road will be constructed to upstream of the barrier for both construction and future maintenance.

Q&A

Provide a short summary of your question.

You have 150 characters left

Provide detailed information relating to your question.

You have 500 characters left

Select a respondent from the list that you would most like to answer your question.

Moderation Policy

These are the people that are listening and responding to your questions.

The Project Team

{{ question.username }} asked

{{question.description}}

{{ answer.respondent.name }}
| Edited

Answer this question

Select the respondent who will be marked as answering the question

Provide the answer to the question. Answer can be saved as draft and published when complete.

No questions found