September 21, 2023 Update

22 September 2023

Work continues on all three organics receiving/processing facilities. The Micro Hydro Solar PV and Grinder/Mixer RFQs have now closed.

In the Columbia Valley, the leachate pond fencing is complete and electrical supply design remains underway.

In the Elk Valley the asphalt paving is now complete. The electrical supply design remains underway.

Planned Work for Next Progress Period

  • Placement of electric MCC room (shipping container) in operational location at the Central Receiving Facility.
  • Planning for receiving pad and lock block headwall installations at all sites.
  • Gravel shouldering around asphalt pads for all sites.