Project Update - May 16, 2024

20 May 2024

Here is the latest project update for the Regional Organics Processing and Receiving Facilities.

Central Site Progress

  • Wireless temperature probes received at the Cranbrook office. This completes the purchase and receipt of all components of the ReoTemp temperature monitoring system
  • RDEK IT is planning on installation of ReoTemp temperature monitoring computers, peripherals and software by the end of May

Columbia Valley Site Progress

  • Wireless temperature probes received at the Cranbrook office. This completes the purchase and receipt of all components of the ReoTemp temperature monitoring system
  • Grinder mixer delivery to site expected this month
  • Site grading, compaction and remediation from seasonal deficiencies has been completed
  • RDEK IT is planning on installation of ReoTemp temperature monitoring computers, peripherals and software by the end of May

Elk Valley Site Progress

  • Wireless temperature probes received at the Cranbrook office. This completes the purchase and receipt of all components of the ReoTemp temperature monitoring system
  • Grinder mixer delivery to site expected by the end of May or early June
  • RDEK IT is planning on installation of ReoTemp temperature monitoring computers, peripherals and software by the end of May

Planned Work for Next Progress Period

  • Modem with SIM card and antenna installation for Columbia and Elk Valley sites
  • ReoTemp computer system portion of temperature monitoring system to each site
  • Grinder/Mixer delivery to Columbia Valley site
  • Most site deficiencies from pre-substantial completion inspection to addressed by the end of May