Here is the latest construction update on the organics receiving and processing facilities:

Central Site Progress

  • The generator for the Micro Hydro Solar PV Project has been delivered and connected
  • Shouldering of Asphalt pad, generator storage pad and relief cut for east end of asphalt pad in process this week
  • Power take off unit supply investigation ongoing

Columbia Valley Site Progress

  • BC Hydro electrical supply design has been completed and power installation is anticipated in the next 6 weeks
  • Lock block headwalls and receiving pad barriers have been placed
  • Shouldering of asphalt pad complete

Elk Valley Site Progress

  • BC Hydro electrical supply design is complete
  • The RDEK has received Statutory Right of Way (SRW) documents for placement of a guy in MoTI Right of Way. The District of Sparwood is working to complete their portion

Planned Work for Next Progress Period

  • Elk Valley site - concrete receiving pad and lock block walls
  • All sites, electrical sub to place distribution wiring from MCC room to blower and lighting locations
  • All sites receipt of blower units for installation
  • All sites receipt of temperature probes
  • Gravel shouldering around asphalt pad at Elk Valley site