Construction Update - January 25, 2024

26 January 2024

Infrastructure going in at the Central site

Warmer conditions over the past few days have made work conditions on site much more favourable. Here is the latest update:

Central Site Progress

  • Micro Hydro Solar PV Project - 15kW generator automatic start kit installation in process. One small part in transit expected to arrive and be installed by early next week
  • Blower controllers have been received and installed and wiring is complete awaiting testing
  • Compost process line wireless temperature probes have been received by general contractor, software yet to be purchased and delivered

Invermere Site Progress

  • BC Hydro electrical supply was completed on Monday January 22
  • Blower units and controllers have been delivered, installed and given a pre inspection test
  • Survey engaged today formal proposal for final survey and as-built drawings to be received next week

Elk Valley Site Progress

  • BC Hydro electrical pole installation started on Monday; however, installation was halted due to site conditions and we will be working with BC Hydro to identify a new approach
  • Blower units and controller have been delivered to site
  • Blower distribution cable feed trench excavation in process
  • Delivery of concrete lock blocks for headwalls has occurred and headwall construction should be complete by end of tomorrow

Planned Work for Next Progress Period

  • Backup generator for Central installed and solar PV system tested and online
  • Receipt of mechanical grinder/mixer at Central site late next week
  • Central IT installation
  • Distribution feed wiring in Sparwood
  • Possible power installation at Sparwood