Construction Update - January 11, 2024

12 January 2024

As construction continues toward a 2024 completion, here is the first update of the new year:

Central Site Progress

  • Micro Hydro Solar PV Project - 15kW generator automatic start kit installation in process
  • Blower units with motors received in Cranbrook and have been delivered to site
  • Compost process line wireless temperature probes have been received by the general contractor

Columbia Valley Site Progress

  • BC Hydro electrical supply design has been completed
    • Terms and conditions of power supply agreement with BC Hydro (BCH) has been completed, internal work order has been issued by BCH anticipate power install by early February or sooner
  • Blower controllers have been delivered and installed

Elk Valley Site Progress

  • BC Hydro electrical supply design is complete
    • Terms and conditions of power supply agreement with BC Hydro (BCH) has been completed, internal work order has been issued by BCH anticipate power install by early February or sooner
  • Blower units have been received and are being stored at the Central composting site
  • Blower controller units have been received and are being stored in Cranbrook
  • Delivery of concrete lock blocks for headwalls has been delayed due to subcontractor mechanical and scheduling issues
  • Concrete receiving pad excavation has been declared a seasonal deficiency and will be executed in the spring

Planned Work for Next Progress Period

  • Backup generator for Central installed and solar PV system tested and online
  • Central IT installation
  • Possible power installation at Invermere and Sparwood