Here is the latest construction update for February 8 for the three organics receiving and processing facilities:

Central Site Progress

  • Micro Hydro Solar PV Project
    • 15kW generator automatic start kit installed
    • Generator installed by RDEK contract electrician
    • Testing/commissioning system is underway
  • Blower controllers have been received and installed and wiring is complete, different wiring is required prior to start up
  • The Grinder/Mixer is expected to be delivered any day
  • Final field survey completed last Friday as-built drawings in process

Columbia Valley Site Progress

  • BC Hydro electrical supply was completed on Monday January 22
  • Blower units and controllers have been delivered, installed and given a pre inspection test
  • Final field survey has been completed as-built drawings in process

Elk Valley Site Progress

  • The RDEK and BC Hydro are working to complete design for the electrical pole installation
  • Blower units and controller delivered to site
  • Blower distribution electrical cable installation and backfill completed
  • Blower units installed behind headwalls
  • Concrete block headwalls have been placed and assembled

Planned Work for Next Progress Period

  • Solar PV system capable of operating
  • BC Hydro re-design potentially complete
  • As-built drawings for all sites
  • Invermere and Fort Steele air distribution piping installed and connected