News

Construction Update - April 4, 2024

5 April 2024

Central Site Progress

  • RDEK electrical subcontractor has completed the blower controls and timer installation
  • RDEK subcontractor has placed order for blower connection pipe sections and blower pipe caps completion is anticipated by April 24
  • Wireless temperature probes purchase is in process
  • RDEK IT is planning on installation of ReoTemp temperature monitoring computers, peripherals and software by the end of April
Columbia Valley Site Progress
  • Grinder/Mixer anticipated delivery date has been revised to the end of April
  • RDEK electrical subcontractor has completed the blower controls and timer installation
  • RDEK subcontractor has placed order for blower connection pipe sections and blower pipe caps completion is anticipated by April 24
  • Wireless temperature probes purchase is in process
  • RDEK IT is planning on installation of ReoTemp temperature monitoring computers, peripherals and software by the end of April

Elk Valley Site Progress

  • Grinder/Mixer anticipated delivery date has been revised to the end of April
  • RDEK electrical subcontractor has completed the blower controls and timer installation
  • RDEK subcontractor has placed order for blower connection pipe sections and blower pipe caps completion is anticipated by April 24
  • Wireless temperature probes purchase is in process
  • RDEK IT is planning on installation of ReoTemp temperature monitoring computers, peripherals and software by the end of April

Planned Work for Next Progress Period

  • Receipt of grinder mixer conveyor belt units for Invermere and Sparwood anticipated by end of April
  • Blower connection to aeration distribution piping
  • Air distribution piping installation for all sites
  • Wireless temperature probe purchase and shipment