August 24, 2023 Update

25 August 2023

Central Site Progress

  • Water deflection berms installed.
  • Micro Hydro RFQ/RFP development is in process.
  • Grinder/mixer RFQ/RFQ is in process.

Invermere Site Progress

  • Asphalt supply, haul, placement and compaction completed.
  • Temporary fence around pond installed and the permanent fencing will be installed in September.
  • Site electrical design meeting was held to establish a plan for electrical supply.
  • Grinder/mixer RFQ/RFQ is in process.

Sparwood

  • Haul, placement and compaction is in process with the top layer of combigrid installed.
  • Pond liner installation to be completed this week.
  • BC Hydro electrical supply design site meeting completed with a plan for overhead electrical supply established.
  • Grinder/mixer RFQ/RFQ is in process

Planned Work for Next Progress Period

  • Asphalt deflection berm for Invermere site.
  • Sparwood asphalt pad pavement.
  • Completion of reinforced structural fill for Sparwood.
  • Electrical design in process for Sparwood and Invermere.
  • Micro Hydro and Grinder/Mixer RFP development continues for all sites.