Here is the latest progress report on the construction of three subregional organics receiving facilities in the RDEK:

Central Site Progress

  • Asphalt paving completed
  • Pond liner installed

Invermere Site Progress

  • Granular supply, haul, placement and compaction completed for reinforced structural fill for asphalt and gravel pad.
  • Site electrical design and quote in process with BC Hydro.

Sparwood

  • Site stripping and base preparations are complete
  • Reinforced structural fill granular supply, haul, placement and compaction is in process
  • Pond shaping and preparations for liner placement are in process
  • BC Hydro electrical supply design is in process.

Planned Work for Next Progress Period

  • Asphalt paving for Columbia Valley Facility and possibly Elk Valley Facility
  • Elk Valley Facility pond shaping and lining
  • Completion of reinforced structural fill for Elk Valley Facility